Control · target 2026-11-14
Production Cutover Readiness
Gate-based readiness for the Production switch to the new OBL Directory.
Status
NOT READY
8 of 12 gates passing · 3 blockers · checklist 4/10
The platform provides assurance evidence. The Bank retains responsibility for the production Go/No-Go decision.
Readiness68%
Critical findings5
Evidence coverage81%
Blockers3
Cutover gates
- PASSSandbox validated; Production change scheduled
- PASSToken endpoint and scopes verified in Sandbox
- PASSOrganisation lookup and certificate validation proven
- PASSChain validated on API Gateway and F5
- PASSEntrust and Keyfactor certificates accepted at the edge
- PASSOCSP and CRL reachable; new Directory host allow-listed in Sandbox
- WARNINGPISP journey not yet run; AISP journey warning
- FAIL5 critical findings open, 3 are cutover blockers
- WARNING81% coverage; target 95%
- PASSRollback plan approved; rehearsal complete
- PASSDashboards and alerts updated
- FAIL3 migration-critical TPP continuity failures remain unresolved.
Existing TPP Continuity sub-gates
Mandatory gate — click a TPP continuity failure to open the affected population
- PASSExisting registrations preserved184 client registrations intact; no mass re-registration dependency detected
- FAILDirectory identity resolutionLegacy Directory lookup remains configured; 1 organisation not found
- PASSEntrust certificate continuity137 Entrust certificates validate against the existing chain
- FAILKeyfactor certificate readinessKeyfactor chain missing from the Open Banking API Gateway trust store
- WARNINGDual trustProven at the load balancer; not yet proven at the gateway
- PASSSSA validationSoftware statement signatures validate against the new Directory JWKS
- WARNINGRole / permission validation4 role differences under investigation
- WARNINGRepresentative end-to-end testing5 of 7 cohorts completed end-to-end
- FAILCritical TPP exceptions3 migration-critical continuity failures remain unresolved
- WARNINGEvidence completeness91% TPP continuity evidence coverage; target 95%
Cutover checklist
4 of 10 complete
Go / No-Go decision
Only Migration Programme Manager, Risk / Compliance and Administrator can record the decision
GO is disabled until all gates pass.