Assess
Assess

Migration Control Library

Structured library of Directory migration controls. Each control traces to tests, findings and evidence.

Pass126
Action required13
Critical5
Not assessed5
Exception0
17 of 17
MethodEvidence
OPS-001Runbooks updatedOperational ReadinessLow2Static analysisPASS112 Sept, 16:05
OPS-002On-call briefedOperational ReadinessLow2Network probeNOT ASSESSED
OPS-003Monitoring dashboards updatedOperational ReadinessMedium2Certificate inspectionPASS109 Sept, 18:05
OPS-004Alerting thresholds tunedOperational ReadinessHigh2Engineer attestationPASS110 Sept, 10:05
OPS-005Rollback plan approvedOperational ReadinessLow2Architecture reviewPASS111 Sept, 11:05
OPS-006Cutover communications planOperational ReadinessLow1Configuration scanPASS12 Sept, 12:05
OPS-007Incident bridge testedOperational ReadinessMedium2API probePASS108 Sept, 13:05
OPS-008Post-cutover hypercare definedOperational ReadinessLow2Static analysisPASS109 Sept, 14:05
OPS-009TPP communications issuedOperational ReadinessLow2Network probeACTION REQUIRED10 Sept, 15:05
OPS-010Change freeze scheduledOperational ReadinessLow2Certificate inspectionPASS111 Sept, 16:05
OPS-011Capacity validatedOperational ReadinessMedium2Engineer attestationPASS112 Sept, 17:05
OPS-012Disaster recovery reviewedOperational ReadinessLow2Architecture reviewPASS108 Sept, 18:05
OPS-013Data retention reviewedOperational ReadinessHigh1Configuration scanPASS109 Sept, 10:05
OPS-014Third-party notifiedOperational ReadinessLow2API probePASS10 Sept, 11:05
OPS-015Cutover rehearsal completedOperational ReadinessMedium2Static analysisPASS111 Sept, 12:05
OPS-016Evidence pack reviewedOperational ReadinessLow2Network probePASS112 Sept, 13:05
OPS-017Go/No-Go criteria agreedOperational ReadinessLow2Certificate inspectionPASS108 Sept, 14:05